Web posted at:
11/01/99 20:20:38 (GMT + 02:00)
|
Number of Stations 21
Type of Stations All Below Ground
Construction Methods Underground Mined-6 Stations
Cut- and- Cover- 15 Stations
Station Configuration Surface Entrances and Station Access Intermediate
- Concourse &Transfer Levels
- Lower Platform Levels
- Two Side Platforms at all stations except Pentagono
- One Center Platform at pentagono
Length of Platforms 110 meters
Revenue Collection Barrier Free Proof-of-Payment System
- PAID/UNPAID Areas Clearly Defined
- Validated Tickets Required
- Ticket Sales Offices
- Automatic Ticket Issuing Machines (ATIMs)
- Ticket Vakidator / Cancelers ( TVCs)
Station Supervision Concourse Station Master
Police Office at Selected Stations
Closed Circuit Television (CCTV)
Public Address System (PA)
Emergency Telephones on Platforms
Environmental Control Forced air Mechanical Ventilation System
Provisions for Future air-conditioning
Vertical Circulation Stairs
Escalators
Elevators from Street to Concourse and
Concourse to Platform for Persons with Special Needs
Passenger Amenities Platform Seating
Public Telephones, Concourse and Platforms
Ash & Trash Bins
Signs & Graphics
Neighborhood and System Maps
Public Lavatories
First Aid Rooms and Facilities
Central Lost & Found Office at Syntagma
Archaeological Displays and Exhibition Areas
|
Next Topics:
Metro Basics
Metro Highlights
Enabling Legislation, Law 1955/91
The Role of Bechtel International
Construction Contract
Geology
Public Utility Relocations
Expropriations of Private Property
Archaeology
Tunnel Construction
Tunnel Boring Machines (TBM)
Pilot Tunnel Project
Station Features
Facilities for Persons with Special Needs
Alignment
|
|
|
|
|
|
|
|